Case study: Carbon black and delayed coker projects at Ruwais Refinery

  • Established in 1999, Abu Dhabi Oil Refining CO [TAKREER] is responsible for managing, operating and developing the downstream oil refining activities of Abu Dhabi National Oil Company [ADNOC]
  • The current capacities of the two refineries in Abu Dhabi Emirate total 485,000 bpsd, with a new 400,000 bpsd expansion project nearing completion at Ruwais
  • ADNOC entered into the refining business modestly with
  • Abu Dhabi Refinery commissioning a 15,000 bpsd plant in 1976; to be replaced by a 60,000 bpsd refinery in 1983 and subsequently expanded to 85,000 in 1992.

Country / Region

United Arab Emirates
Energy Generation Oil Oil Gas

Presentation Date

Tuesday, May 14, 2013 - 11:30

Speakers

Panellist

Presentation PDF